Nevsun Resources provides Bisha update
by Jo Black

Nevsun Resources Ltd. provides an update to shareholders on its Bisha project. Recent milestones achieved by the Bisha Mining Share Company (BMSC), the Company’s Eritrean subsidiary, include:
- Bisha Mining License Issued, announced January 8, 2008
- Bisha Mining Agreement Signed, announced December 12, 2007
- Agreement for State Participation Signed, announced October 29, 2007
The boards of Nevsun Resources and BMSC have recently approved the decision to progress the Bisha project through to project construction. Senet Engineering of South Africa was selected in 2007 as the preferred contractor for the project following an international bidding process, and has been actively engaged with BMSC in the preliminary and detailed engineering design for the Bisha Mine since mid 2007. During that time, BMSC’s Project Manager has been located in Senet’s Johannesburg office liaising with Senet staff. Senet established an office in Asmara during Q4 2007.
A contract with Senet defining their continuing role as the EPCM (Engineering, Procurement, and Construction Management) contractor for the development of the Bisha Mine in Eritrea will be completed shortly. The longest lead items and hence the critical path limitation for the development of the Bisha Mine are the SAG and ball mills. BMSC has selected the crusher and mill supplier for the project following an international bidding process and is in the process of finalizing orders.
Nevsun has received a substantial provisional payment from ENAMCO, the Eritrean National Mining Corporation, in connection with the State participation arrangements announced in October 2007, such that Nevsun cash position at month end January 2008 is approximately US$40 million. The Company is well financed to continue with the development of the Bisha Mine with its partner ENAMCO.
BMSC has commenced actively seeking project debt financing for the Bisha project with the assistance of Endeavour Financial. The Bisha feasibility study (completed Q4 2006) shows the project to be financially robust with low operating costs throughout the mine life. If the mine were to commence operating now, at current metal prices the project would have a payback of less than one year.
The Bisha Mine development project is currently expected to commence production mid 2010. The Bisha feasibility was completed by AMEC Americas in Q4 of 2006 and provided for a 2 million tonne per year milling facility and an open pit mine with a minimum 10 year life. The first two years of production will focus on mining and processing the high grade (8.0 g/t Au) surface oxide cap (top 35m of deposit) to the Bisha VMS (volcanogenic massive sulphide) deposit producing approximately 450,000 oz of gold and 750,000 oz of silver each year. The following three years will focus on processing the 4.4% copper supergene massive sulphides which lie immediately below the oxide cap (next 30m of the deposit) and the rest of the mine life will centre on processing the primary massive sulphides (7.2% Zn, 1.1% Cu, 0.76 g/t Au and 54.0 g/t Ag).
Related posts to: Nevsun Resources provides Bisha update
Miranda Gold provides exploration update ...
Silver resources increase 143% at Pitarrilla’s Breccia Ridge Zone ...
Dutch Gold retains David Brown & Associates ...
NovaGold financial results and projects update ...
Tara Gold updates San Miguel project ...
Latest Metals News:
Gold ends session lower in New York, but gains on week
Gold prices retreat after setting new intraday high
Gold closes at $1,666 per ounce in New York trade
Gold prices at new records on disappointing US data
Gold prices lower but comes off session lows on manufacturing data
Gold sets new intraday, closing highs to end trading week in New York
Copper rises; precious metals prices see declines
Gold prices drop on profit-taking, stronger US dollar
$1,616.80 per troy ounce: Another record high for gold
Gold trades as high as $1,624.30 per ounce in New YorkPrevious: « Great Western Minerals updates activities
Next: Sunridge appoints new director »
Visited 3405 times, 2 so far today